LONG DISTANCE DISCHARGING WORKS OF DREDGED SOIL BY PLUG FLOW MIXING METHOD IN PIPE LINES
-
- UEZONO Akira
- JAPAN SOCIETY OF CIVIL ENGINEERS
-
- TAKEZAWA Kazuhiko
- 元運輸省 第一港湾建設局 伏木富山港湾工事事務所
-
- TSUKADA Shouichi
- 元運輸省 第一港湾建設局 伏木富山港湾工事事務所
-
- TAKAHASHI Kunio
- JAPAN SOCIETY OF CIVIL ENGINEERS
Bibliographic Information
- Other Title
-
- 管中混合による浚渫土砂固化処理工法の長距離圧送実験
- カン チュウ コンゴウ ニ ヨル シュンセツドシャコカ ショリ コウホウ ノ チョウキョリ アッソウ ジッケン
Search this article
Abstract
Various kinds of plug flow mixing method which is developed to mix dredged soil with cement during soil conveying work by plug flow have been invented. The discharging distance experienced, however, was only limited to several hundred meters. Recently, a long distance discharging work of approximately one km with three kinds of plug flow mixing method have been conducted to confirm applicability of this method for soil disposal on land at Fushiki-toyama port.<br>This paper presents technical particulars including unconfined compression strength of the cement mixed soil of the work.
Journal
-
- Doboku Gakkai Ronbunshu
-
Doboku Gakkai Ronbunshu 2000 (651), 37-45, 2000-06-20
Japan Society of Civil Engineers
- Tweet
Details 詳細情報について
-
- CRID
- 1390001205310638464
-
- NII Article ID
- 130003801583
- 10004444592
-
- NII Book ID
- AN10014020
-
- ISSN
- 18827187
- 02897806
-
- NDL BIB ID
- 5401640
-
- Data Source
-
- JaLC
- NDL
- Crossref
- CiNii Articles
-
- Abstract License Flag
- Disallowed