A study on the application of fuzzy theory to power system planning and operation problems 電力系統の運用計画問題へのファジィ理論の適用に関する研究
Access this Article
Search this Article
Author
Bibliographic Information
- Title
-
A study on the application of fuzzy theory to power system planning and operation problems
- Other Title
-
電力系統の運用計画問題へのファジィ理論の適用に関する研究
- Author
-
Gibson, Graeme Robert
- Author(Another name)
-
ギブソン, グレアム ロバート
- University
-
北海道大学
- Types of degree
-
博士 (工学)
- Grant ID
-
甲第3846号
- Degree year
-
1996-03-25
Note and Description
博士論文
Table of Contents
- ABSTRACT / (0003.jp2)
- TABLE OF CONTENTS / p5 (0010.jp2)
- DEDICATION / p2 (0007.jp2)
- ACKNOWLEDGEMENTS / p3 (0008.jp2)
- CHAPTER / p1 (0013.jp2)
- 1.INTRODUCTION / p1 (0013.jp2)
- 1.1 Uncertainty in Power System Planning and Operation / p1 (0013.jp2)
- 1.2 Introduction to Planning and Operation Problems / p5 (0017.jp2)
- 1.3 Objective of the Present Work / p8 (0020.jp2)
- 1.4 Synopsis of Each Chapter / p10 (0022.jp2)
- 2.FUZZY THEORY APPLICATION / p13 (0025.jp2)
- 2.1 Introduction to Fuzziness / p13 (0025.jp2)
- 2.2 Fuzzy Tools / p15 (0027.jp2)
- 2.3 Fuzzy Theory Application to Conventional Multistage Decision Techniques / p24 (0036.jp2)
- Chapter Summary / p32 (0044.jp2)
- 3.THERMAL GENERATING UNIT MAINTENANCE SCHEDULING APPROACH BASED ON FUZZY THEORY (Application Example #1) / p33 (0045.jp2)
- 3.1 Overview / p33 (0045.jp2)
- 3.2 Maintenance Scheduling by Equalisation / p34 (0046.jp2)
- 3.3 Application of Fuzzy Theory / p38 (0050.jp2)
- 3.4 Numerical Examples / p48 (0060.jp2)
- Chapter Summary / p57 (0069.jp2)
- 4.HYDROTHERMAL SCHEDULING APPROACH BASED ON FUZZY DYNAMIC PROGRAMMING(Application Example #2) / p59 (0071.jp2)
- 4.1 Overview / p59 (0071.jp2)
- 4.2 Proposed Fuzzy Dynamic Programming / p60 (0072.jp2)
- 4.3 New Fuzzy DP Approach for Hydrothermal Scheduling / p61 (0073.jp2)
- 4.4 Adopting the Features of the Proposed Method / p69 (0081.jp2)
- Chapter Summary / p86 (0098.jp2)
- 5.OPTIMAL GENERATION MIX PLANNING BASED ON FUZZY DYNAMIC PROGRAMMING(Application Example #3) / p87 (0099.jp2)
- 5.1 Overview / p87 (0099.jp2)
- 5.2 Problem Formulation / p87 (0099.jp2)
- 5.3 New Fuzzy DP Generation Mix Approach / p89 (0101.jp2)
- 5.4 Numerical Examples / p92 (0104.jp2)
- Chapter Summary / p103 (0115.jp2)
- 6.CONCLUSIONS / p104 (0116.jp2)
- Overview / p104 (0116.jp2)
- Fuzzy Theory Application to Maintenance Scheduling / p104 (0116.jp2)
- Fuzzy Dynamic Programming Application to Hydrothermal Scheduling / p105 (0117.jp2)
- Fuzzy Dynamic Programming Application to Optimal Generation Mix / p107 (0119.jp2)
- REFERENCES / p109 (0121.jp2)